Question: please help I don't understand this at all, here is the chart to refer to, ill give you extra ratings! For the network below, calculate
please help I don't understand this at all, here is the chart to refer to, ill give you extra ratings!

| For the network below, calculate for each task, BCWP, BCWS, ACWP, CV, SV, CPI, SPI. | ||||||||||||||
| Calculate these numbers for the entire project as well. | ||||||||||||||
| | ||||||||||||||
| For each of the seven tasks that make up the project above, assume the following: | ||||||||||||||
| TASK | Percent Complete | Expenditures/Day | Actual Expenditures to Date | Duration | ||||||||||
| A | 100% | $1,000 | $10,000 | 11 | ||||||||||
| B | 100% | $1,200 | $9,000 | 9 | ||||||||||
| C | 30% | $1,000 | $4,000 | 7 | ||||||||||
| D | 20% | $1,500 | $5,000 | 6 | ||||||||||
| E | 40% | $1,500 | $3,000 | 5 | ||||||||||
| F | 0% | $1,000 | $0 | 9 | ||||||||||
| G | 0% | $1,200 | $0 | 4 | ||||||||||
| TASK | TOTAL BUDGET | %COMP | ACWP | BCWS | BCWP | CV | SV | CPI | SPI | |||||
| (AC) | (PV) | (EV) | ||||||||||||
| A | $11,000 | 100% | $10,000 | |||||||||||
| B | 100% | $9,000 | ||||||||||||
| C | 30% | $4,000 | ||||||||||||
| D | 20% | $5,000 | ||||||||||||
| E | 40% | $3,000 | ||||||||||||
| F | 0% | $0 | ||||||||||||
| G | 0% | $0 | ||||||||||||
| Totals | ||||||||||||||
| For each task and for the entire project (bottom line) calculate BCWS, BCWP, CV, SV, CPI, SPI. | ||||||||||||||
| Project is 12 days old--12 business days have transpired | ||||||||||||||
| BAC = | EAC = | |||||||||||||
| TAC = | ETAC = | |||||||||||||
| Comments on the status of your project: | ||||||||||||||