Question: please help I don't understand this at all, here is the chart to refer to, ill give you extra ratings! For the network below, calculate
please help I don't understand this at all, here is the chart to refer to, ill give you extra ratings!

| For the network below, calculate for each task, BCWP, BCWS, ACWP, CV, SV, CPI, SPI. | ||||||||||
| Calculate these numbers for the entire project as well. | ||||||||||
| | ||||||||||
| For each of the seven tasks that make up the project above, assume the following: | ||||||||||
| TASK | Percent Complete | Expenditures/Day | Actual Expenditures to Date | Duration | ||||||
| A | 100% | $1,000 | $13,000 | 10 | ||||||
| B | 100% | $1,200 | $9,000 | 9 | ||||||
| C | 30% | $1,000 | $4,000 | 7 | ||||||
| D | 20% | $1,500 | $5,000 | 6 | ||||||
| E | 40% | $1,500 | $3,000 | 5 | ||||||
| F | 0% | $1,000 | $0 | 9 | ||||||
| G | 0% | $1,200 | $0 | 4 | ||||||
| Fill out the table below: | ||||||||||
| TASK | TOTAL BUDGET | %COMP | ACWP | BCWS | BCWP | CV | SV | CPI | SPI | |
| (AC) | (PV) | (EV) | ||||||||
| A | $10,000 | 100% | $13,000 | |||||||
| B | 100% | $9,000 | ||||||||
| C | 30% | $4,000 | ||||||||
| D | 20% | $5,000 | ||||||||
| E | 40% | $3,000 | ||||||||
| F | 0% | $0 | ||||||||
| G | 0% | $0 | ||||||||
| Totals | $34,000 | |||||||||
| Project is 14 days old--14 business days have transpired | Calculate the following: | |||||||||
| BAC = | EAC = | |||||||||
| TAC = | ETAC = | |||||||||