For the network below, calculate for each task, BCWP, BCWS, ACWP, CV, SV, CPI, SPI.
Calculate these numbers for the entire project as well.
For each of the seven tasks that make up the project above, assume the following:
TASK Percent Complete Expenditures/Day Actual Expenditures to Date Duration
A 100% $1,000 $13,000 10
B 100% $1,200 $9,000 9
C 30% $1,000 $4,000 7
D 20% $1,500 $5,000 6
E 40% $1,500 $3,000 5
F 0% $1,000 $0 9
G 0% $1,200 $0 4
Fill out the table below:
TASK TOTAL BUDGET %COMP ACWP BCWS BCWP CV SV CPI SPI
(AC) (PV) (EV)
A $10,000 100% $13,000
B 100% $9,000
C 30% $4,000
D 20% $5,000
E 40% $3,000
F 0% $0
G 0% $0
Totals $34,000
Project is 14 days old--14 business days have transpired Calculate the following:
BAC = EAC =
TAC = ETAC =
B/9 E/5 A/10K on K G/4 F/9 D/6 B/9 E/5 A/10K on K G/4 F/9 D/6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!