Question: Earned Value Analysis Consider the following project information (the first 4 columns below) and the project status at the end of week 4 (columns 5

Earned Value Analysis

Consider the following project information (the first 4 columns below) and the project status at the end of week 4 (columns 5 and 6)

Earned Value Analysis Consider the following
Immediate Duraon Actual Cost Completion Saws at Task Predecessor (week) Budget ($K) ($K) the end of Week 4 A - 2 26 18 100% B - 3 9 4 40% C A 2 14 12 50% D C 2 6 2 10% E B 2 12 0.5 10% F C 3 9 5 30% G A 5 15 7 30% H D,E,F,G 1 5 0 0% i H 1 20 0 0%