Question: Earned Value Exercise Complete the following problems: 1. The following project is at the end of its first week. Find the cost and schedule variances,

Earned Value Exercise Complete the following problems: 1. The following project is at the end of its first week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion. Task Predecessors A B C D E None None A A B ,C Duration in days 2 3 2 5 6 Planned Value ($) 500 1000 200 600 1200 Actual Cost ($) 650 1500 300 600 550 Percent Complete 100 100 50 20 10 2. The following project is at the end of its third week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion. Task Predecessors A B C D E F G H None A A A B ,C C F G Duration in days 3 5 2 5 6 10 7 8 Planned Value ($) 600 1000 200 1000 1200 10000 700 1600 Actual Cost ($) 650 1500 300 600 1200 12000 0 0 Percent Complete 100 100 100 100 100 75 0 0 3. Mary is the project manager for a web design project for Newberry Pet Foods. So far in the six weeks (of the twelve week project), Mary's team has completed five tasks which had a combined planned value of $7800. However, the team spent $8200 to complete those tasks. She has five additional tasks to complete the project. What are the PV, EV, AC, CV, SV, CPI, and SPI for Mary's project? 4. Consider the following information: PV=6500 EV=5000 AC=7200 BAC=32000 Expected Duration=12 weeks Calculate the following: CV = SV __________________ CPI __________________ SPI __________________ EAC __________________ Duration at Completion _______________

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!