Question: Earned Value Analysis You are working as construction labor and have 10 sections of fence to paint. It is estimated that it will take you
Earned Value Analysis You are working as construction labor and have 10 sections of fence to paint. It is estimated that it will take you 2 hours per section and you are seheduled to work 2 hours a day. You are paid $10 per bour. After 5 work days you have spent 6 hours and completed 4 sections of fence. Calculate the following: BAC= PV= EV= AC= SV= SPI= CV= CMI- EACBAC/CH= YAC ETC=EACAC=TCP(BACEV)/(AACAC)= What does Earned Value Analysis tell us about this project? If appropriate, what corrective action would you recommend