Question: Earned Value Assignment - Fill in the yellow highlighted boxes on this spreadsheet. The following bar chart shows the activities ( A to J )
Earned Value Assignment Fill in the yellow highlighted boxes on this spreadsheet.
The following bar chart shows the activities A to J for a month project for $
After months, A B C F are completed with an actual cost of $
Activity and have not yet started.
What is the status of the project in terms of the budget? Is it overbudget or underbudget?
How is the project schedule ahead or behind Provide the variances in numbers and percentage.
tableActivityBudgeted Cost,Month Month Month Month Month Month A$$B$$D$$E$$F$$H$$I$$J$
Find the budgeted cost of work performed, budgeted cost of work scheduled, and variances.
State whether the project is overbudget or underbudget, ahead or behind schedule.
Fill in the yellow boxes
tabletableState whether the project is overbudget or underbudget, ahead or behind schedule.Fill in the yellow boxes
tableACWP monthsBCWS monthsBCWP monthstabletable$
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock