Question: need help ving activities are required in starting up a 2. The following activities ar new plant: Immediate Predecessor Activity Activity Time lot moooD |

need help
need help ving activities are required in
ving activities are required in starting up a 2. The following activities ar new plant: Immediate Predecessor Activity Activity Time lot moooD | IMMO WNA NNW E, C, D a. Draw a network for this project. b. Make a forward and backward pass to determine ES, LS, EF, and LF. c. Calculate slack. d. Prepare a Gantt chart for this project