Question: Earned Value: Exercise# 3 Continued At the status date ( Week 2 0 ) , you are also given the following information: P V =

Earned Value: Exercise#3
Continued
At the status date (Week 20), you are also given the following information:
PV=$512,000
AC=$530,000
EV=$429,000
(a) Determine cost, schedule and time variances (i.e. CV, SV, TV).
(b) Determine Cost and schedule performance indices (i.e. CPI and SPI).
(c) Comment on the status of this project.
(d) Given the budgeted cost at completion of $990,000, determine ETC and EAC. Also if the project was planned to finish on Week 47, forecast the new completion date and sketch the lines for forecast AC and forecast EV.
36
 Earned Value: Exercise#3 Continued At the status date (Week 20), you

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!