Question: Earned Value: Exercise# 3 Continued At the status date ( Week 2 0 ) , you are also given the following information: P V =
Earned Value: Exercise#
Continued
At the status date Week you are also given the following information:
$
$
$
a Determine cost, schedule and time variances ie CV SV TV
b Determine Cost and schedule performance indices ie CPI and SPI
c Comment on the status of this project.
d Given the budgeted cost at completion of $ determine ETC and EAC. Also if the project was planned to finish on Week forecast the new completion date and sketch the lines for forecast AC and forecast EV
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
