Question: Earned value recognizes both completion scheduled and cost pull up a video on you tube y That covers this concept or also look in Text
Earned value recognizes both completion scheduled and cost pull up a video on you tube y
That covers this concept or also look in Text
Given the following information for a oneyear project, answer the following questions. Assume you have actual
and earned value data at the end of the second month. Recall that PV is the planned value, EV is the earned
value, is the actual cost, and BAC is the budget at completion.
$
$
$
BAC$
What is the cost variance, schedule variance, cost performance index CPI and schedule performance index
SPI for the project?
Cost variance
Schedule variance
I
I
How is the project progressing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
Use the CPI to calculate the estimate at completion EAC for this project. Is the project performing better or
worse than planned?
Use the SPI to estimate how long it will take to finish this project.
The estimated time to finish the project
Sketch the earned value chart for this project, using Figure as a guide. Assume the data for month is half
of the values given for PV EV and AC at the end of month
The chart should resemble the following figure, available in file exxls
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock