Question: eBook Net Present Value A project has estimated annual net cash flows of $12,500 for five years and is estimated to cost $47,500. Assume a
Net Present Value A project has estimated annual net cash flows of $12,500 for five years and is estimated to cost 547,500 , Assume a minimum acceptable rate of return of 15%. Use the Present Value of an Annuity of $1 at Compound Interest table below. Net present value of the project (round to the nearest dollar) Present value index (rounded to two decimal places) Went value indek. If required, use the mirus sign to indicate a negotive net present value