Question: Eight jobs are to be processed through a single machine. The precedence relationships that must be satisfied are: 2 - > 6 - > 3

Eight jobs are to be processed through a single machine.
The precedence relationships that must be satisfied are:
2->6->3
1->4->7->8
The processing times and due dates are:
Job Processing time Due date
125
234
3213
416
5412
6310
7215
8219
Determine the sequence in which these jobs should be done in order to minimize the maximum lateness subject to the precedence restrictions.
Based on the optimal sequence: (Enter integer only)
The first job to be processed is Job
.
The third job to be processed is Job
.
The fourth job to be processed is Job
.
The fifth job to be processed is Job
.
The eighth job to be processed is Job

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!