Question: Element Observed time ( min ) 0 . 3 5 0 . 6 0 0 . 8 6 6 The readings in the table below

Element
Observed time (min)
0.35
0.60
0.86
6 The readings in the table below were taken by the snapback timing method of direct time study to produce a certain subassembly. The task was performance rated at 85%. In addition to the above regular elements, an irregular element must be included in the standard each rack holds 20 mechanism plates and has move the rack (which now holds the subcompleting 20 subassemblies, the operato a mew empty rack into position at the workstation. assemblies) to the aisle and then move 2.90min and the operator was performance rated at This irregular element was timed at 20 mine (a) the normalized time for the cycle, (b) the 80%. The PFD allowance is 15% per of parts produced by the operator, if he or she works at standard time, and (c) the num tof 6hr and 57min during the shift.
Element and Description
Pick up mechanism plate from rack and place in fixture.
Assemble motor and fasteners to front side of plate.
0.42
0.28
Move to other side of plate.
0.11
0.56
0.33
Assemble two brackets to plate.
0.40
Assemble hub mechanism to brackets.
Remove plate from fixture and place in rack.
nalues in the table below were obtained ask. All elements manual repetitive n irregular ele-
 Element Observed time (min) 0.35 0.60 0.86 6 The readings in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!