Question: EMSE 6805 - Assignment One Background You have been identified as the lead Systems Engineer ( SE ) and placed in a Program Management O
EMSE 6805
-
Assignment
One
Background
You have
been
identified as the lead
Systems Engineer (
SE
)
and placed
in a
Program Management O
ffice (PMO)
to correct and get an ailing
program back on track. The effort has already been re
-
baselined multiple
times but still continues to suffer technical & cost issues and to a lesser
degree schedule pressure
.
You have brought in your team of SE experts
to assess
and recommend to the
program
manager if this program should
be cancelled or continued
and of course why or why not.
Scenario
This is a three (3) year contract awarded to your firm by large
automotive manufacturer. Originally
this was a two (2) phase effort to a)
mature a technology and b) get it ready for production. Specifically, this
was regarding to a new versatile hydrogen fuel cell engine to be used in
a wide line of automobiles. This was originally a $25
-
million
-
dollar
e
ffort but has swelled to $50M and the bleeding hasn't stopped.
The first issue occurred during qualification of the fuel cell 'stack' or the
heart of the engine. The qualification samples were having low yield
rates and your firm couldn't get adequate par
ts in for testing. The stacks
are made by another vendor and the low yield rates couldn't be
explained or root caused because the sample set was too low. They
stated that similar prior runs had much higher yield rates and the only
way to identify root caus
e is to run more stacks. This takes considerable
time (4
-
5 months) and additional funding.
You have about 30 parts and
you need 50. There are 30 additional ones that have yet go through
testing, but you believe that those too will have the same problem.
T
he issues continued when your firm tried to mount the 30 good parts.
There were several workmanship issues. In some issues areas were
grounded that shouldn't have been and re
-
work is necessary to correct
the problem. Re
-
work isn't risk free and there is a
chance of damaging
the good stacks when you try to remove them. One of the areas also
suffered an ESD event, but that has since been corrected with a new
EMSE 6805
-
Assignment
One
HVAC system. The ESD event was due to low humidity.
Because of these issues you haven't been able to
run a full suite of
testing to see how good horsepower and fuel economy will be. However,
the initial results were very encouraging and already showed orders of
magnitude improvement over legacy designs. This is exactly what the
large automotive manufactur
er is looking for. These positive results
have kept the team going and maintained morale.
Your Firm
Is an established large corporation with solid PM
a
nd SE
practices. They
are fairly high level but none the less they are in place and do a good job
at bounding
corporate procedures. The PM on this effort to
-
date has
been only part time
as have the lead SE
. This is still seen as a somewhat
minor project for your company and since no production contract was
awarded, a part time unexperienced PM was assigned to cut costs.
Additionally, there aren
'
t many tailo
red SE
processes
such as risk and
schedules and most are at a high level from the corporate firm.
Additionally,
areas in systems engineering were also underfunded.
We
'
re not even sure how much money was spent on SE.
Given your
firms vast resources, a lot of matrixed support was pulled from other
areas in a part
-
time
setting. Your org structure has been heavily matrixed
with few overall de
dicated people to this effort alone.
You are on a cost
plus award fee contract with this vendor. You haven't been getting any
award fee because of your performance and have been submitting cost
overrun proposals as they come in and asking for performance
e
xtensions. Thus far, all have been granted, but you believe the customer
is wary and is considering cancelling the effort.
Path Forward
Although this is just one project, your firm's credibility is on the line.
Having an effort cancelled by the customer
is a bad for publicity. At the
same time, this isn't a large project for your firm but if this goes into
production, you will naturally be sole sourced and long term lucrative
EMSE 6805
-
Assignment
One
revenue is all but guaranteed.
Your job is to formulate a recommendation to the
seniors as to the best
course of action. Do we abandon this effort and save face or continue
with a new course of action?
You are expected to provide an executive summary
(5
-
10 pages)
report
to corporate seniors. Although questions and discussions could be raised,
this report is expected to stand on it
'
s own be self supported. All
assumptions, facts, inputs, outputs, analysis, etc should be identified.
The report should first and foremost be accurate but also professional in
appearance.
The seniors would at a
minimum
like to know the following:
1.
How did we get here?
2.
What were the biggest issues that caused these overruns?
3.
Where are we in the project
lifecycle
? What phase?
4.
Did we have process issues? If so, which ones.
5.
Did we follow solid SE / PM guidelines
? Why and why not?
6.
What are the biggest risks facing the effort moving forward? What
is he best course of
mitigation?
7.
If we do move forward, what is the get well plan? What changes
and corrective actions
do y
ou recommend implementing.
8.
How do we propose this to the customer?
9.
Is this a win
-
win situation?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
