Question: End Item B(2) D(3) E(2) F(3) G(2) (2) H(4) E(2) The following table lists the components needed to assemble an end item, lead times, and

End Item B(2) D(3) E(2) F(3) G(2) (2) H(4) E(2)

End Item B(2) D(3) E(2) F(3) G(2) (2) H(4) E(2) The following table lists the components needed to assemble an end item, lead times, and quantities on hand. G H Item End Lead time (week) Amount on hand 10 10 25 35 30 5 Given the following diagram, an order for the end item is scheduled to be shipped at the start of week 20. What is the latest week that the order can be started and still be ready to ship on time