Question: Enter this into an excel file Develop a material requirements plan for end item P and its components, given the following tree. Assume that all

Enter this into an excel file
Develop a material requirements plan for end item P and its components, given the following tree. Assume that all lead times are one week, and that lot-for-lot ordering is used except for item F, which is ordered in multiples of 100 units.
50 units of P should be available at the start of week 5 and at the start of week 8. Beginning inventories are: 20 Ps,30 As, and 100 Fs.
Scheduled receipts are: 100 Fs at the start of week 1.