Question: Entity A commenced a contract to build a non-current asset for Entity B in the year ended 30 September 2018. The contract price was agreed

Entity A commenced a contract to build a non-current asset for Entity B in the year ended 30 September 2018. The contract price was agreed at $1,500 and the total expected costs of the contract have been confirmed as $800. Entity A will satisfy the performance obligation over time.

The following figures were correctly recognised in the Statement of Profit or Loss for the year ended 30 September 2018:

  • Revenue $450
  • Cost of Sales $240
  • Profit $210

The following figures are also relevant in relation to this contract:

  • 2018 2019   
  • Costs incurred to date $325 $575
  • Work certified to date $450                $1,050

Entity A recognises progress on a work certified basis.


REQUIRED:

Measure the contract revenue and contract cost for Entity A in its Statement of Profit or Loss for the year ended 30 September 2019.

Step by Step Solution

3.38 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To measure the contract revenue and contract cost for Entity A in its Statement of Profit or Loss for the year ended 30 September 2019 follow these st... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!