Question: ERSIONACKNEXT Problem 10.17 Wildhorse Mills management is evaluating two alternative heating systems. Costs and projected energy savings are given in the following table. The firm

ERSIONACKNEXT Problem 10.17 Wildhorse Mills management is evaluating two alternative heating systems. Costs and projected energy savings are given in the following table. The firm uses 11.5 percent to discount such project cash flows. Year System 100 System 200 $1,409,300 -$2,070,600 266,810 893,100 441,230 579,400 625,600 449,20o 731,540 723,700 What is the NPV of the systems? (Enter answers to 0 decimal places, e.g. 5,275.) using negative amounts using negative sign, e.g. 45.25. Do not round discount factors and intermediate calculations. Round NPV of system 100 is s NPV of system 200 is s Which system should be chosen? Wildhorse should choose Ozen Show Work Click if you would like to Show Work for this question: LINK TO TEXT ere to search