Question: ES 12 EF 21 B 9 ES EF 20 ES 12 29 LF 0 LS EF 50 29 D 12 21 ? LF 29 LS

ES 12 EF 21 B 9 ES EF 20 ES 12 29 LF 0 LS EF 50

ES 12 EF 21 B 9 ES EF 20 ES 12 29 LF 0 LS EF 50 29 D 12 21 ? LF 29 LS 50 LF LS ES 12 EF 29 17 12 29 LS LF A simple CPM network has four activities, A, B, C, and D as shown in the above. Calculate the latest finish time (LF) for the node A