Question: Question 16 (1 point) ES 12 EF 38 B 26 ES 0 EF 12 LS ES 38 LF EF 59 A 12 D 21 LS

Question 16 (1 point) ES 12 EF 38 B 26 ES 0 EF 12
Question 16 (1 point) ES 12 EF 38 B 26 ES 0 EF 12 LS ES 38 LF EF 59 A 12 D 21 LS LF ? LF LS ES 12 EF 34 22 LF In a critical path method (CPM) network, activity nodes are shown in the above figure. Calculate the latest finish time (LF) for the final node D. Note: Round your final answer to an integer