Question: Question 12 (1 point) ES 12 EF 21 B 9 EF 20 ES 0 29 LF ES 29 EF 50 12 LS 12 D 21

Question 12 (1 point) ES 12 EF 21 B 9 EF 20 ES 0

Question 12 (1 point) ES 12 EF 21 B 9 EF 20 ES 0 29 LF ES 29 EF 50 12 LS 12 D 21 ? 29 50 LS LF LS LF ES 12 EF 29 17 12 LS 29 LF A simple CPM network has four activities, A, B, C, and D as shown in the above. Calculate the latest finish time (LF) for the node A. Your