Question: Estimate project status on the reporting date based on the data presented in Table 2. Table 2 Project Status report on 08.04 Activity Duration, weeks

Estimate project status on the reporting date based on the data presented in Table 2.

Table 2

Project Status report on 08.04

Activity

Duration,

weeks

Date of start*

Activity budgeted cost, Euro

Actual cost on 08.04, Euro

Work performed on 08. 04, %

Work planned on 08.04, %

PV

EV

A

4

1.02

600

900

100

B

5

1.02

1500

1400

100

C

4

08.03

600

450

90

D

5

08.03

1000

900

80

E

2

15.04

200

-

-

F

3

15.04

600

-

-

G

4

8.05

1200

-

-

H

5

8.04

750

200

20

* Assume that month lasts 4 weeks, the first week begins 1st day, the second 8th, the third - the 15th, the fourth - 23 th.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!