Question: Estimate project status on the reporting date based on the data presented in Table 2. Table 2 Project Status report on 08.04 Activity Duration, weeks
Estimate project status on the reporting date based on the data presented in Table 2.
Table 2
Project Status report on 08.04
| Activity | Duration, weeks | Date of start*
| Activity budgeted cost, Euro | Actual cost on 08.04, Euro | Work performed on 08. 04, % | Work planned on 08.04, % | PV | EV |
| A | 4 | 1.02 | 600 | 900 | 100 |
|
|
|
| B | 5 | 1.02 | 1500 | 1400 | 100 |
|
|
|
| C | 4 | 08.03 | 600 | 450 | 90 |
|
|
|
| D | 5 | 08.03 | 1000 | 900 | 80 |
|
|
|
| E | 2 | 15.04 | 200 | - | - |
|
|
|
| F | 3 | 15.04 | 600 | - | - |
|
|
|
| G | 4 | 8.05 | 1200 | - | - |
|
|
|
| H | 5 | 8.04 | 750 | 200 | 20 |
|
|
|
* Assume that month lasts 4 weeks, the first week begins 1st day, the second 8th, the third - the 15th, the fourth - 23 th.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock