Question: Estimate the time it will take to complete the 4th unit of a mult-unit job involving a large assembly if the initial unit required 80

Estimate the time it will take to complete the 4th unit of a mult-unit job involving a large assembly if the initial unit required 80 hours and the learning pecentage is: a. 72 percent b) 87 percent c