Question: Estimated Task Time Task ID Task Name Predecessor Cost / Day Total Cost 8 A Site Evaluation 150 1200 10 B Initial Design 200 2000
| Estimated Task Time | Task ID | Task Name | Predecessor | Cost / Day | Total Cost |
| 8 | A | Site Evaluation |
| 150 | 1200 |
| 10 | B | Initial Design |
| 200 | 2000 |
| 12 | C | Design Approval | A,B | 100 | 1200 |
| 5 | D | Order Materials | C | 300 | 1500 |
| 12 | E | Initiate Foundation Work | C | 80 | 960 |
| 14 | F | Design and Install Electrical | D | 60 | 840 |
| 8 | G | Design and Install Plumbing | D | 200 | 1600 |
| 6 | H | Design and Install HVAC | F,G | 300 | 1800 |
| 12 | I | Machine Installation | E,F | 120 | 1440 |
| 4 | J | Task Name | I, H | 150 | 600 |
Problem 1 - Develop a Gantt chart of the project. Please highlight in some way the critical path on your Gantt chart. What is the critical path? You may use Excel or pencil and paper or any other method you prefer.
Problem 2 - After Day 11 the following field report is provided. Determine and provide all metrics. In one or two sentences, what is your assessment of the project status based upon the metrics.
| Field Report Day 11 | ||
| Activity | % Complete | Incurred Cost |
| A | 100 | 1400 |
| B | 100 | 1900 |
| C | 20 | 300 |
| D | 0 |
|
| E | 0 |
|
| F | 0 |
|
| G | 0 |
|
| H | 0 |
|
| I | 0 |
|
| J | 0 |
|
Thank you for your help.