Question: EV AC = Cost Variance. Therefore if EV = AC , the Cost Variance is zero ( i . e . The project is on
EV AC Cost Variance. Therefore if EV AC the Cost Variance is zero ie The project is on budget but not necessarily on schedule, as there is not enough information on schedule variance Trend Analysis is BEST described as: