Question: EV AC = Cost Variance. Therefore if EV = AC , the Cost Variance is zero ( i . e . The project is on
EV AC Cost Variance. Therefore if EV AC the Cost Variance is zero ie The project is on budget but not necessarily on schedule, as there is not enough information on schedule variance Trend Analysis is BEST described as:
Group of answer choices
Analyzing performance of similar projects over time
Examining project performance over time
Calculating Earned Value
Calculating Cost Variance
Group of answer choices
There is no issue you are both talking about the same thing You are correct and the stakeholder is just not getting it
The stakeholder is correct and you're just not getting it
You are correct and the stakeholder is just not getting it
You are both incorrect and need to explore other options.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock