Question: Evaluate the progress of a project with the following table: Task Budget Scheduled Progress Performed Progress ACWP A $ 2 0 0 1 0 0

Evaluate the progress of a project with the following table:
Task
Budget
Scheduled Progress
Performed
Progress
ACWP
A
$200
100%
100%
$200
B
$500
100%
100%
$500
C
$200
50%
80%
$100
D
$400
100%
100%
$450
E
$300
33.33%
66.67%
$100
F
$400
75%
30%
$80
The whole project is ____(ahead of/behind by how much) schedule. Please round to the closest integer.