Question: Evaluate the progress of a project with the following table: Task Budget Scheduled Progress Performed Progress ACWP A $200 100% 100% $200 B $500 100%

Evaluate the progress of a project with the following table:

Task

Budget

Scheduled Progress

Performed

Progress

ACWP

A

$200

100%

100%

$200

B

$500

100%

100%

$500

C

$200

50%

80%

$100

D

$400

100%

100%

$450

E

$300

33.33%

66.67%

$100

F

$400

75%

30%

$80

A) The whole project is ____ (ahead of / behind by how much) schedule. For example, if your answer is $100 ahead of schedule, put down 100 ahead in the blank; if your answer is $100 behind schedule, put down 100 behind in the blank.

b)The whole project is ____ (above / under by how much) budget. For example, if your answer is $100 above budget, put down 100 above in the blank; if your answer is $100 under budget, put down 100 under in the blank.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!