Question: Evaluate the progress of a project with the following table: Task Budget Scheduled Progress Performed Progress ACWP A $200 100% 100% $200 B $500 100%
Evaluate the progress of a project with the following table:
| Task | Budget | Scheduled Progress | Performed Progress | ACWP |
| A | $200 | 100% | 100% | $200 |
| B | $500 | 100% | 100% | $500 |
| C | $200 | 50% | 80% | $100 |
| D | $400 | 100% | 100% | $450 |
| E | $300 | 33.33% | 66.67% | $100 |
| F | $400 | 75% | 30% | $80 |
Question #1-
The whole project is ____ (ahead of / behind by how much) schedule. For example, if your answer is $100 ahead of schedule, put down 100 ahead in the blank; if your answer is $100 behind schedule, put down 100 behind in the blank.
Question #2-
The whole project is ____ (above / under by how much) budget. For example, if your answer is $100 above budget, put down 100 above in the blank; if your answer is $100 under budget, put down 100 under in the blank.