Question: Even though we are 3 0 days into the project, we still see that we have only 9 0 percent of this activity complete. The
Even though we are days into the project, we still see that we have only percent of this activity complete. The second activity relates to company donations and is scheduled to run for days starting on day and extending through day We estimate that even though we should have approximately percent or more precisely of this activity complete, it is actually only percent complete. This part of the project was scheduled to bring in $ in donations. The final activity is for matching funds. This activity is scheduled to run the last days of the project and has not started. It is scheduled to bring in an additional $ So far $ has actually been brought in on the project.
Calculate the schedule variance, schedule performance index, cost actually value in this case variance, and cost performance index. Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round your "performance index" values to decimal places.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock