Question: Everly Gibbs, as the project manager is working on a project for the Airline industry and is developing a project schedule network diagram. Consider the

Everly Gibbs, as the project manager is working on a project for the Airline industry and is developing a project schedule network diagram. Consider the following data for a network: IQ TIM Activity Predecessor Successor Duration Start E 2 Days B Start 5 Days Start 3 Days D Start 2 Days E A 1 4 Days F B End 3 Days G C J 3 Days H D End 5 Days E End 4 Days J G End 5 Days What is the Float of activity G? 0