Question: EVM 1 - What is the Planned Value ( PV ) for this project at this point in time? EVM 1 - What is the

EVM1- What is the Planned Value (PV) for this project at this point in time?
EVM1- What is the Planned Value (PV) for this project at this point in time?
$10,000*80%= $8,000
$6,000*80%= $4,800
$6,000*50%= $3,000
$10,000*50%= $5,000