Question: EVM example For a small manufacturing project consider the following : - Baseline cost for 100% of project = $80,000 - Planned progress as per

EVM example

For a small manufacturing project consider the following :

- Baseline cost for 100% of project = $80,000

- Planned progress as per schedule baseline = 40%

- Your calculation at 47.5% physical progress .

- Actual expenditure = $48,000

1- Calculate the required fund , assuming the same calculated projection of cost performance, that must be obtained for the remaining work (ETC)

2- Interpret schedule and cost performance for this contractor, consider KPIs = 0.90 is the target .

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!