Question: For a small manufacturing project consider the following : - Baseline cost for 100% of project = $80,000 - Planned progress as per schedule baseline

For a small manufacturing project consider the following : - Baseline cost for 100% of project = $80,000 - Planned progress as per schedule baseline = 40% - Your calculation at 47.5% physical progress . - Actual expenditure = $48,000 1- Calculate the required fund , assuming the same calculated projection of cost performance, that must be obtained for the remaining work (ETC) 2- Interpret schedule and cost performance for this contractor, consider KPIs = 0.90 is the target
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
