Question: For a small manufacturing project consider the following : - Baseline contact value = $80,000 - Planned progress (as per schedule baseline ) = 40%

For a small manufacturing project consider the following : - Baseline contact value = $80,000 - Planned progress (as per schedule baseline ) = 40% - Your Data Date @ 47.5% physical progress . - Actual expenditure = $48,000 1- Calculate the required fund , assuming the same calculated projection of cost performance, that must be obtained for the remaining work (ETC) 2- Interpret schedule and cost performance for this contractor, consider KPIs = 0.90 is a Corporate target . 0