Question: EX: - the following data about the project tasks, network, and crash times/costs .calculate the cost of the project at all tie durations until you

EX: - the following data about the project tasks,

EX: - the following data about the project tasks, network, and crash times/costs .calculate the cost of the project at all tie durations until you can no longer crash the project any further. Activity Preceded by Normal time(weeks) None 5 10 13 ||||| A A B B,D C F Normal cost ($) 500 1200 3600 300 1000 2400 700 Crash Crash time cost (weeks ($) 4 600 6 2000 11 4800 1 600 4 1400 8 5400 5 700 E F G 3 5 10 5