Question: EX5-5 (Algo) Below Is a project WBS with cost... Below is a project WBS with cost apportioned by percent If the total project cost is

EX5-5 (Algo) Below Is a project WBS with cost... Below is a project WBS with cost apportioned by percent If the total project cost is estimated to be $610,000, what are the estimated costs for the following deliverables? (Round the final answers to the nearest dollar.) Router systems project $610,090 Definition Design Implementation 9% 42% 49% Objectives Requirements Inputs Outputs Files Interfaces Programming In-house testing Customer testing and review 4% 5% 4% 2% 5% 11% 20% 39% 10% a. Design? b. Programming? G. In-house testing