Question: EX5-5 (Algo) Below is a project WBS with cost... Below is a project WBS with cost apportioned by percent. If the total project cost is
EX5-5 (Algo) Below is a project WBS with cost... Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to be $610,000, what are the estimated costs for the following deliverables? (Round the final answers to the nearest dollar) Router systems project $610,000 Design Definition Implementation 51% 10% 39% Objectives RequirementsInputs Outputs Files Interfaces Programming In-house tosting Customer testing and review 19% 5% 5% 4% 2% 3% 11% 43% 8% a b. Design? Programming? In-house testing? c