Question: EX5-5 (Algo) Below is a project WBS with cost... Below is a project WBS with cost apportioned by percent. If the total project cost is

 EX5-5 (Algo) Below is a project WBS with cost... Below is

EX5-5 (Algo) Below is a project WBS with cost... Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to be $610,000, what are the estimated costs for the following deliverables? (Round the final answers to the nearest dollar.) Router systems project $610,000 Definition Design Implementation - 10% 39% 51% Objectives Requirements Inputs Outputs Files Interfaces Programming in-house testing Customer testing and review 5% 5% 4% 2% 3% 11% 19% 43% 8% a b. Design? Programming? In-house testing? C

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!