Question: EX8-1 (Static) Consider a project with the... Consider a project with the accompanying Gantt chart. Stella is your only electrical engineer and she is


EX8-1 (Static) Consider a project with the... Consider a project with the accompanying Gantt chart. Stella is your only electrical engineer and she is responsible for activities 3 and 4, which overlap. Level the project so that Stella is only working a maximum of 8 hours each day. What would the new Gantt chart look like? What would be the new project completion date? ID Task Mode Task Name Duration Jan 5, 20 S M Jan 12, 20 T WTFS S M T W T F S Jan 19, 20 SM T 1 Activity 1 2 days 2 Activity 2 3 days 3 Activity 3 5 days Stella Stella 4 Activity 4 3 days 5 Activity 5 2 days ces 6 Activity 6 2 days New project completion date would be EX8-2 (Static) Bjorn and Thor are plumbers... Bjorn and Thor are plumbers who have been scheduled to work on the construction of a new school building. Just before the start of the project, Bjorn broke his arm and cannot work on the project. Now Thor has to handle his own activities as well as Bjorn's. Level the project Gantt chart so that Thor is responsible for activities 3, 4, 6, and 7. How will the project completion date be affected? Feb 24, '19 Mar 3, '19 SMTWTFS SMTWTFS SMTWTF ID 0 Task Mode Task Name Feb 17, 19 T S 1 Activity 1 2 activity 2 3 Activity 3 4 activity 4 5 Activity 5 6 Activity 6 7 4 Activity 7 8 t Activity 8 New project completion date would be Bjorn Thor Bjorn Thor
Step by Step Solution
There are 3 Steps involved in it
To solve these problems we need to adjust the Gantt charts to address resource constraints for Stell... View full answer
Get step-by-step solutions from verified subject matter experts