Question: please answer the new project completion date EX8-1 (Static) Consider a project with the... Consider a project with the accompanying Gantt chart. Stella is your
please answer the new project completion date
EX8-1 (Static) Consider a project with the... Consider a project with the accompanying Gantt chart. Stella is your only electrical engineer and she is responsible for activities 3 and 4, which overlap. Level the project so that Stella is only working a maximum of 8 hours each day. What would the new Gantt chart look Nike? What would be the new project completion date? D Task Task Name Duration 0 Jan 5, 20 M Jan 12.20 Mode Jon 19.20 IM 1 + + 2 4 5 Activity Activity 2 Activity Activity Acts Act 2 days say 5 days 3 days 2 days 2 days Stofa Stola * Now project conclation date would be