Question: EX8-14 (Algo) Given the time-phased work packages... Given the time-phased work packages and network, complete the baseline budget form for the project. Soccer Toy Project
EX8-14 (Algo) Given the time-phased work packages...
Given the time-phased work packages and network, complete the baseline budget form for the project.
| Soccer Toy Project Cost By Week ($000) | ||||||
| 1 | 2 | 3 | 4 | 5 | ||
| A Design prototype | 11 | 0 | 0 | 0 | 0 | |
| B Build prototype | 15 | 10 | 10 | 10 | 0 | |
| C Order parts | 14 | 5 | 0 | 0 | 0 | |
| D Prepare production | 3 | 10 | 22 | 16 | 0 | |
| E Prepare marketing | 4 | 6 | 0 | 6 | 0 | |
| F Assemble and test | 16 | 10 | 18 | 18 | 0 | |
| G Launch | 18 | 10 | 0 | 0 | 0 | |
Enter the appropriate values in the truncated portion of the budget form shown below.
rev: 10_28_2020_QC_CS-236340
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock