Question: Exam 2: Final Examination Problem 1: The table below lists the activities and precedence relationships for a house building project. Activity Mnemonic Activity Time (weeks)

Exam 2: Final Examination Problem 1: The table below lists the activities and precedence relationships for a house building project. Activity Mnemonic Activity Time (weeks) Predecessors Dig Basement Dig 3 Pour Foundation Found 4 Dig Pour Basement Floor Pourb 2 Found Install Floor Joists Joists 3 Found Install Walls Walls 5 Found Install Rafters Rafters 3 Walls, Pourb Install Flooring Floor A Joists Rough Interior Rough 6 Floor Install Roof Roof 7 Rafters Finish Interior Finish 5 Rough, Roof Landscape Scape 2 Pourb, Walls 1) Sketch the pert diagram for this project. 2) Determine the length of the critical path and determine the activities that lie on the critical path