Question: Examine Work Breakdown Structure, organization, schedule & budget, tracking performance and reporting variances. Prompt: Assume the following project is being prepared for progress review at

Examine Work Breakdown Structure, organization, schedule & budget, tracking performance and reporting variances.
Prompt:
Assume the following project is being prepared for progress review at the end of the third quarter.
According to the budget baseline, all tasks should be completed except Task 8, which should be about 30% complete at this
time. The project manager reports, however, that all tasks are completed except Task 8, which is only about 10% complete.
Required: Assuming that actual costs to date total $240,000, compute (formula with the result) and evaluate (in narrative form)
the following:
a. BAC
b. BCWS (PV)
c. EV
d. AC
e. CV and CPI
f. SV and SPI
g. ETC and EAC
h. TCl.
discuss, in general terms, a possible change to the project that could be made to hasten the completion of a task that is behind schedule, such as Task 8.
Examine Work Breakdown Structure, organization,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!