Question: Example 2 . 2 9 A project has the following activities as given in Table 2 . 1 0 7 and other activity - related

Example 2.29
A project has the following activities as given in Table 2.107 and other activity-related characteristics.
Table 2.107 Project activity details
Activity Predecessor(s) To
(Weeks) Tm (Weeks) Tp
(Weeks)
A 4716
B 1515
C A 61230
D A 258
E C 51117
F D 3615
G B 3927
H E, F 147
I G 41928
(a) Draw the PERT network.
(b) Identify the critical path.
(c) Determine the mean project completion times.
(d) Find the probability that the project is completed in 36 weeks.
(e) If the project manager wishes to be 99% sure that the project is completed, how many days
should be provided for the project work?
Solution:
(b) A C E H (c)37 weeks (d)42.07%(e)48.63 ~ 49 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!