Question: Example 2 . 2 9 A project has the following activities as given in Table 2 . 1 0 7 and other activity - related
Example
A project has the following activities as given in Table and other activityrelated characteristics.
Table Project activity details
Activity Predecessors To
Weeks Tm Weeks Tp
Weeks
A
B
C A
D A
E C
F D
G B
H E F
I G
a Draw the PERT network.
b Identify the critical path.
c Determine the mean project completion times.
d Find the probability that the project is completed in weeks.
e If the project manager wishes to be sure that the project is completed, how many days
should be provided for the project work?
Solution:
b A C E H c weeks de ~ weeks