Question: Example for you: TEST YOURSELF Assuming two separate 8 hour shift, compute cycle time to obtain output of 600 unit per day. e precedence I
Example for you: TEST YOURSELF Assuming two separate 8 hour shift, compute cycle time to obtain output of 600 unit per day. e precedence I otal tme 25s 2 Draw precedence diagram " network" 3 determine the minimum number of work station requirement? "Minimum number of workers" 4* Assign tasks to work stations using the most following tasks method 5 compute idle time of the process 6 compute the overall efficiency of the process or of the line