Question: EXERCICE ON SCHEDULING (25 Marks) Apply the First Come First Serve sequencing rule to these five jobs Job Job Work (processing) time Job Due Date

EXERCICE ON SCHEDULING (25 Marks) Apply the First Come First Serve sequencing rule to these five jobs Job Job Work (processing) time Job Due Date (Days) (Days) A 6 8 B 2 6 C 8 18 D 3 15 E 9 23 EXERCICE ON MAINTENANCE AND RELIABILITY (25 Marks) How does machine design contribute to either increasing or alleviating the maintenance