Question: Exercise 1: Develop the AON and AOA networks based on the following project schedule how long does it takes to complete this project. Draw both
Exercise 1:
Develop the AON and AOA networks based on the following project schedule how long does it takes to complete this project. Draw both AON and AOA networks and identify the critical path.
| ID | ACTIVITY | DUR. (days) | Predecessor(s) |
| 1 | A | 5 |
|
| 2 | B | 5 | 1 |
| 3 | C | 5 |
|
| 4 | D | 5 | 1 |
| 5 | E | 5 | 1 |
| 6 | F | 5 | 3,4 |
| 7 | G | 5 | 1 |
| 8 | H | 5 | 5,6,7 |
| 9 | I | 5 | 6,8 |