Question: Exercise 2: Develop the AON networks based on the following project schedule how long does it takes to complete this project. Draw the AON network
Exercise 2:
Develop the AON networks based on the following project schedule how long does it takes to complete this project. Draw the AON network and identify the critical path.
| ID | ACTIVITY | DUR. (days) | Predecessor(s) |
| 1 | A | 5 |
|
| 2 | B | 5 | 1 |
| 3 | C | 5 |
|
| 4 | D | 5 | 1 |
| 5 | E | 5 | 1 |
| 6 | F | 5 | 3,4 |
| 7 | G | 5 | 1 |
| 8 | H | 5 | 2,5 |
| 9 | I | 5 | 2,5 |
| 10 | J | 5 | 9 |
| 11 | K | 5 | 8 |
`