Question: Exercise 2: Develop the AON networks based on the following project schedule how long does it takes to complete this project. Draw the AON network

Exercise 2:

Develop the AON networks based on the following project schedule how long does it takes to complete this project. Draw the AON network and identify the critical path.

ID

ACTIVITY

DUR. (days)

Predecessor(s)

1

A

5

2

B

5

1

3

C

5

4

D

5

1

5

E

5

1

6

F

5

3,4

7

G

5

1

8

H

5

2,5

9

I

5

2,5

10

J

5

9

11

K

5

8

`

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!