Question: Exercise 1: Draw the activity diagram based on the tasks, durations and dependencies given below. Given the following table, draw the activity network diagram and
Exercise 1: Draw the activity diagram based on the tasks, durations and dependencies given below. Given the following table, draw the activity network diagram and calculate how many days will it take to complete the project? Task (T) Duration (days) Dependencies T1 5 T2 6 T1 (M1) T3 12 T4 17 T2, T3 (M2) T5 18 T4 (M3), T3 T6 5 T5 (M4)
can you solve it please